File #: 18-7954    Version: 1 Name: Fleet Service Center Change Order/Amendment No. 5 with Modern Contractors in the amount of $20,452 for entry gate island provision, structural steel framing additions, fan steel support, removal of GFCI requirement, added manhole, concrete grade beam addi
Type: Agenda Item Status: Consent Agenda
File created: 5/25/2018 In control: Engineering
On agenda: 6/5/2018 Final action: 6/5/2018
Title: Fleet Service Center Change Order/Amendment No. 5 with Modern Contractors in the amount of $20,452 for entry gate island provision, structural steel framing additions, fan steel support, removal of GFCI requirement, added manhole, concrete grade beam addition, existing fire hydrant adjustment, elimination of concrete paving, landscape changes, ADA door operator, pipe stands at roof surface, increased masonry reinforcing and framing connection for metal panels
Attachments: 1. 615.27.pdf, 2. File Summary
From
max

Title
Fleet Service Center Change Order/Amendment No. 5 with Modern Contractors in the amount of $20,452 for entry gate island provision, structural steel framing additions, fan steel support, removal of GFCI requirement, added manhole, concrete grade beam addition, existing fire hydrant adjustment, elimination of concrete paving, landscape changes, ADA door operator, pipe stands at roof surface, increased masonry reinforcing and framing connection for metal panels

Presenter
Andy Henning, Senior Building and Construction Projects Manager

Recommended Action
Approve

Analysis
On December 13, 2016 the City Council awarded the Construction Manager at Risk (CMAR) contract to Modern Contractors for pre-construction services in the amount of $1000. This award provided for CMAR services including development of project estimates, preliminary construction schedules, value engineering proposals and constructability review during the Design Phase.

The current Change Order/Amendment No. 5 in the amount of $20,452 is divided as follows:
1. $3,495 for island concrete, curbs and bollards for card reader access at entry gate 2
2. $1,189 for miscellaneous steel lintel support required along with structural steel column connection modification
3. $1,675 for added steel support required for large industrial fan provisions
4. -$270 for removal of GFCI provisions where not required by code
5. $4,100 for additional sewer line manhole necessary for future maintenance and access
6. $5,192 for coordination of new concrete tilt wall and grade beam construction with unforeseen existing building pier cap provision
7. $500 for elevation adjustment of existing hydrant to coordinate with new concrete island
8. -$4,605 for removal of concrete pour-back at new storm line installation due to existing deteriorating asphalt condition needing attention by the City
9. -$6,435 for removal of a portion of new concrete planned in order to coordinate with the existing elevation of t...

Click here for full text