Change Order/Amendment No. 10 with Lee Lewis Construction, Inc. in the amount of $797,413 for mechanical louver revisions, basement areaway wall adjustments, door changes from wood to fiberglass, door hardware adjustments to coordinate with planned operations, structural concrete pier depth reconciliation, removal of shower doors, glazing type changes in glass doors, elimination of mechanical room glazing, addition of door access into lazy river wave generation room, expansion of synthetic turf to include outdoor Epic Fit space, basketball wood flooring revision, exterior video board addition and lock modification for locker room patron lockers
Presenter
Andy Henning, Senior Building and Construction Projects Manager
Recommended Action
Approve
Analysis
On December 9, 2014 the City Council awarded the Construction Manager at Risk (CMAR) contract to Lee Lewis Construction, Inc. for pre-construction services in the amount of $20,000. This award provided the CMAR services including development of project estimates, preliminary construction schedules, value engineering and constructability review during the Design Phase.
The current Change Order/Amendment No. 10 in the amount of $797,413 is divided as follows:
1. $8,958 for mechanical louver revisions for durability
2. $6,290 for basement areaway wall adjustments for maintenance access
3. $4,287 for door changes from wood to fiberglass in areas potentially impacted by chemicals
4. $21,390 for door hardware adjustments to coordinate with planned facility operations/access
5. $308,672 for structural concrete pier depth reconciliation due to varying geotechnical strata layer profile
6. -$13,397 for removal of shower doors and replacement with shower curtains
7. -$10,227 for reduction of glazing type specified for glass doors based on code requirements
8. -$8,935 for removal of window into mechanical room
9. $8,799 for added doorway into wave generation vault for lazy river
10. $6,457 for ex...