Engineering services amendment/Change Order No. 5 with Team Consultants and Reed Engineering will increase the engineering geotechnical and material testing services to a maximum contract of $800,000 for each firm
Presenter
Romin Khavari, City Engineer
Recommended Action
Approve
Analysis
On July 15, 2014, the City of Grand Prairie approved the geotechnical and material testing services fee ordinance and service contracts. Developers in Grand Prairie will be required to deposit the geotechnical and material testing fees up front to have a third party engineering consultant working for the City to perform this work. On City Capital Improvement Projects, the City will incur the cost to have this work performed also by these firms as part of the project.
Staff recommended that this work be performed by three consulting firms. Specific work assignment for the consultants will be at the City’s discretion and to be based upon size of project, complexity of project, firm’s familiarity with the area, workload, conflict of interest, and past performance.
The selection of the three engineering consulting firms was through the Request for Qualifications (RFQ) process. Request for qualifications were sent to sixteen (16) Engineering Geotechnical and Material Testing consulting firms with responses received from eleven (11) firms. Five (5) firms were selected for shortlist interviews. Based on qualifications and laboratory facilities, the three firms recommended were Alliance Geotechnical, Team Consultants and Reed Engineering respectively.
Change order No. 1 was approved by City Council on April 21, 2015 (15-4565) to address future material testing needs. This change order raised the maximum current contract from $150,000 to $350,000. Contract termination date was set as May 31, 2016.
Change order No. 2 was approved by City Council on February 2, 2016 (16-5338) to address material testing needs. This change order raised the maximu...