File #: 15-4321    Version: 1 Name: Ordinance; Final Reconciliation for Hunter Ferrell with Dallas County
Type: Ordinance Status: Adopted
File created: 1/7/2015 In control: Transportation
On agenda: 1/20/2015 Final action: 1/20/2015
Title: Ordinance amending FY 2014/2015 Capital Improvements Project Budget; Final Reconciliation to Dallas County in the additional amount of $205,806 for Hunter Ferrell Rd Participation #47601 (Beltline - MacArthur, Incl 1700' of Story)
Attachments: 1. FIS 05503803
From
max

Title
Ordinance amending FY 2014/2015 Capital Improvements Project Budget; Final Reconciliation to Dallas County in the additional amount of $205,806 for Hunter Ferrell Rd Participation #47601 (Beltline - MacArthur, Incl 1700' of Story)

Presenter
Walter Shumac, Director of Transportation Services

Recommend Action
Approve

Analysis
The City Council at their October 16, 2007 meeting approved Resolution 4268 which authorized Dallas County Public Works to design, acquire right-of-way and construct Hunter-Ferrell Road between Beltline Road and MacArthur Boulevard as well as obligate Grand Prairie to fund $4,187,400 for the project. The City of Irving also approved a Resolution approving the same for their portion that lies within their city.

When the design was complete and the right-of-way acquisition was nearing completion, Dallas County submitted an invoice in the amount of $1,004,011.54 for our share of the design and right-of-way. Funding was available from TIF #1 in the amount of $3,312,820 and moved to the Street Capital Projects Fund (400192) per City Council action (10-0317). With the approval of the Ordinance, the funds were appropriated and available to reimburse Dallas County for this current request and future requests for payment.

In February of 2012, a resolution was approved by City Council (10-0891) in the amount of $220,352 for add alternate enhancements which included such items as a monument sign at the city limit line with each city's name and log, additional landscaping, additional streetscaping and custom railing for the bridge. This brought the agreement total to $4,407,752.

Dallas County has now completed the construction with Grand Prairie participation totaling $4,613,557.40. Additional funding in the amount of $205,805.40 is currently requested to complete Grand Prairie's participation on the Hunter Ferrell Road project with Dallas County.

Financial Consideration
Funding in the amount of $205,806 is available as fo...