Analysis
On February 6, 2018, a contract was awarded to Make It Ready in the amount of $75,095 for Peninsula PID sign and lamp post replacements and repairs. Because the total of this amendment is over $25,000, this change cannot be implemented without City Council authorization.
This proposed Change Order No. 1 is for sign and lamp post replacements and repairs in Peninsula PID.
This change order will not change the term of this contract. The expiration date will be January 31, 2019.
Financial Consideration
Funds for this contract are available from annual assessments adopted by the City Council on September 19, 2017, which are estimated to generate $1,357,061 for the fiscal year.