From
Lee Harriss
Title
Change Order/Amendment No.1 for Kraftsman Commercial Playgrounds & Water Parks at Lake Parks PID, Playground Installation in the total amount of $53,057.45
Presenter
Lee Harriss, Special District Administrator
Recommended Action
Approve
Analysis
On May 14, 2019, a construction contract was awarded to Kraftsman Commercial Playgrounds & Water Parks in the amount of $45,035.22 for the Lake Parks PID playground installation with only City Manager approval. Because this amendment increases the contract value beyond the statutory authority amount ($50,000) delegated by the City Council, this change cannot be implemented without City Council authorization.
This proposed Change Order No. 1 is for installation of a steel shelter with ADA accessible table.
This change order will not change the term of this construction contract. The expiration date will be April 30, 2020.
Financial Consideration
Funding in the amount of $53,057.45 is available in the Lake Parks PID fund 321792-68151-LPPLG (Construction).