File #: 18-8332    Version: 1 Name: Warmack Library Change Order/Amendment No. 3 with Pogue Construction in the amount of $96,838.74 for added structural steel framing, metal stud wall framing adjustments, existing restroom renovations, floor drain provision in mechanical room, entry ramp a
Type: Ordinance Status: Adopted
File created: 10/4/2018 In control: Engineering
On agenda: 10/16/2018 Final action: 10/16/2018
Title: Warmack Library Change Order/Amendment No. 3 with Pogue Construction in the amount of $96,838.74 for added structural steel framing, metal stud wall framing adjustments, existing restroom renovations, floor drain provision in mechanical room, entry ramp and vestibule changes, mechanical unit concrete pad adjustments with landscape changes, storm drainage realignment, partition wall allowance reimbursement credit, new acoustical ceiling tile support grid and insulation of piping at restrooms
Attachments: 1. 18-8332 Warmack Library.pdf
From
max

Title
Warmack Library Change Order/Amendment No. 3 with Pogue Construction in the amount of $96,838.74 for added structural steel framing, metal stud wall framing adjustments, existing restroom renovations, floor drain provision in mechanical room, entry ramp and vestibule changes, mechanical unit concrete pad adjustments with landscape changes, storm drainage realignment, partition wall allowance reimbursement credit, new acoustical ceiling tile support grid and insulation of piping at restrooms

Presenter
Andy Henning, Senior Building and Construction Projects Manager

Recommended Action
Approve

Analysis
On August 15, 2017 the City Council awarded the Construction Manager at Risk (CMAR) contract to Pogue Construction for pre-construction services in the amount of $7,500. This award provided for CMAR services including development of project estimates, preliminary construction schedules, value engineering proposals and constructability review during the Design Phase.

The current Change Order/Amendment No. 3 in the amount of $96,838.74 is divided as follows:
$14,732.41 for additional miscellaneous structural steel framing required and masonry brick ledge at the new south programming addition
$1,471.60 for metal stud wall framing adjustments in order to coordinate with code-required structural steel cross bracing
$72,432.35 for complete renovation of the existing restrooms previously not planned for in the overall project scope
$6,826.58 for the addition of a new floor drain in the previously existing concrete slab area where the new mechanical room will be located
$5,482.24 for the addition of a concrete access ramp at the front entry to the facility to supplement the existing ADA ramp currently located to the south of the main entry approach
$1,143.34 for concrete work and landscaping to rotate and hide new mechanical equipment to be located immediately outside existing glazing of the facility
$3,952.92 for storm drain piping adjustments to...