File #: 18-8465    Version: 1 Name: Change Order/Amendment No.2 for Ridgeline Electric for Peninsula PID
Type: Agenda Item Status: Consent Agenda
File created: 11/16/2018 In control: Finance
On agenda: 12/11/2018 Final action: 12/11/2018
Title: Change Order/Amendment No.2 for Ridgeline Electric, LLC for Peninsula PID electrical installation, maintenance, and repair services in the total amount of $54,075 (Council Districts 4 and 6)
Attachments: 1. Exhibiit A-PID Budget-Peninsula FY19.pdf

From

Lee Harriss

 

Title

Change Order/Amendment No.2 for Ridgeline Electric, LLC for Peninsula PID electrical installation, maintenance, and repair services in the total amount of $54,075 (Council Districts 4 and 6)

 

Presenter

Lee Harriss, Special District Administrator

 

Recommended Action

Approve

 

Analysis

On January 18, 2018, a contract was awarded to Ridgeline Electric, LLC in the amount of $20,000 for PID electrical installation, maintenance, and repair services, and Change Order No. 1 in the amount of $20,000 was approved on May 21, 2018.

 

This proposed Change Order No. 2 is for electrical installation, maintenance, and repair services in Peninsula PID

 

This change order will not change the term of this contract. The expiration date will be December 31, 2018.

 

Financial Consideration

Funds for this contract are available from annual assessments adopted by the City Council on September 18, 2018, which are estimated to generate $1,534,046 for the fiscal year.