From
Lee Harriss
Title
Change Order/Amendment No.2 for Ridgeline Electric, LLC for Peninsula PID electrical installation, maintenance, and repair services in the total amount of $54,075 (Council Districts 4 and 6)
Presenter
Lee Harriss, Special District Administrator
Recommended Action
Approve
Analysis
On January 18, 2018, a contract was awarded to Ridgeline Electric, LLC in the amount of $20,000 for PID electrical installation, maintenance, and repair services, and Change Order No. 1 in the amount of $20,000 was approved on May 21, 2018.
This proposed Change Order No. 2 is for electrical installation, maintenance, and repair services in Peninsula PID.
This change order will not change the term of this contract. The expiration date will be December 31, 2018.
Financial Consideration
Funds for this contract are available from annual assessments adopted by the City Council on September 18, 2018, which are estimated to generate $1,534,046 for the fiscal year.