File #: 17-6619    Version: 1 Name: Change Order/Amendment No. 2 with Klutz Construction, LLC for Sir Roland Drive Wastewater Improvements and Slope Repairs
Type: Agenda Item Status: Consent Agenda
File created: 3/24/2017 In control: Engineering
On agenda: 4/18/2017 Final action: 4/18/2017
Title: Change Order/Amendment No. 2 with Klütz Construction, LLC in the negative amount of ($67,397.00) for Sir Roland Drive Wastewater Improvements and Slope Repairs
Attachments: 1. 17-6619 Sir Roland.pdf

From

max

 

Title

Change Order/Amendment No. 2 with Klütz Construction, LLC in the negative amount of ($67,397.00) for Sir Roland Drive Wastewater Improvements and Slope Repairs

 

Presenter

Ron McCuller, Director of Public Works and Romin Khavari, City Engineer

 

Recommended Action

Approve

 

Analysis

On July 12, 2016, the City of Grand Prairie awarded a construction contract to Klütz Construction, LLC in the amount of $807,855.50 and approved a 5% contingency of $40,393.00 for a total of $848,248.00 for the Sir Roland Drive Wastewater Improvements and Slope Repairs project. 

 

Change Order/Amendment No. 2 in the negative amount of ($67,397.00) provides for the following: Added work for the repair of a damaged landscape light, the removal and replacement of additional damaged sod in the yard at 530 Sir Roland Drive, an 8” concrete curb along an existing flume between 530 and 533 Sir Roland Drive in order to improve drainage and prevent possible erosion adjacent to the flume, installation of additional Asian jasmine plants along the construction access path behind 530 Sir Roland Drive, and reconciliation of some pay items based on revised quantities. Total increase for Change Order/Amendment No. 2 are $16,300; Total decreases are -$83,697 for a net of negative -$67,397 and cumulative of $99,997.

 

Change Order/Amendment No. 1 for $29,250 was approved and executed on November 14, 2016 and included the installation of additional rock rip rap in order to prevent erosion at additional areas along the stream bank, testing equipment for the manta ray anchors installed as part of the stone gabion wall, and tree removal of some dead trees that had fallen into the stream channel and could potentially inhibit flow of the stream during a high rainfall event.

 

The revised overall project completion date for this construction contract is Monday, May 1, 2017.

 

Financial Consideration

No funding is required for this amendment/change order No. 2.