Skip to main content
File #: 19-8639    Version: 1 Name: Fire Station 4+6 Change Order/Amendment No. 2 with Key Construction in the amount of $105,183.26
Type: Agenda Item Status: Consent Agenda
File created: 1/25/2019 In control: Engineering
On agenda: 2/5/2019 Final action: 2/5/2019
Title: Change Order/Amendment No. 2 for Fire Station 6 with Key Construction in the amount of $105,183.26 for Fire Station 6 plumbing revisions, increased electrical provisions/adjustments, permit/weather delays, sanitary sewer manhole abandonment/new location installation, overhead door notification lights with power and implementation of a fire protection system for the area of new construction
Attachments: 1. 617.04 FS 4 and 6
From
max

Title
Change Order/Amendment No. 2 for Fire Station 6 with Key Construction in the amount of $105,183.26 for Fire Station 6 plumbing revisions, increased electrical provisions/adjustments, permit/weather delays, sanitary sewer manhole abandonment/new location installation, overhead door notification lights with power and implementation of a fire protection system for the area of new construction

Presenter
Andy Henning, Senior Building and Construction Projects Manager

Recommended Action
Approve

Analysis
On June 5, 2018 the City Council awarded the Construction Manager at Risk (CMAR) contract to Key Construction for pre-construction services in the amount of $15,000. This award provided for CMAR services including development of project estimates, preliminary construction schedules, value engineering proposals and constructability review during the Design Phase.

The current Change Order/Amendment No. 2 in the amount of $105,183.26 is divided as follows:
$52,097.30 for added utilities for fire suppression system
$1,500.00 for added notification lighting at equipment bay doors
$11,888.00 for General Conditions due to schedule extension based on inclement weather and permit delays
$1,702.76 for removal of abandoned manhole
$19,000.00 for fire sprinkler system
$2,480.00 for electrical changes due to final design coordination items
$1,938.00 for added plumbing and natural gas line to outdoor courtyard
$8,482.00 for Construction Manager overhead and profit percentages
$2,744.20 for Payment and Performance Bond to cover increased construction cost associated with this Change Order/Amendment
$3,351.00 for relocation of ATS and Oncor meter position

Change Order/Amendment No. 1 in the amount of $4,400,000 was approved by City Council on August 7, 2018 (18-8082) for the Guaranteed Maximum Price (GMP) for the addition to Fire Station 6 scope of work defined in the Komatsu Architects Construction Documents package as competitively bid by Subcontractors...

Click here for full text