Fleet Service Center Change Order/Amendment No. 7 with Modern Contractors in the amount of $28,953.39 for spiral ductwork, restroom air conditioning, natural gas connections, site grading changes, added demolition, wood furring, energy compliance additions, grouting of existing door frame, GFCI receptacles, air reel addition, canopy steel, door hardware changes, exterior painting/miscellaneous electrical changes adding power, temporary office trailer provisions and allowance reimbursement
Presenter
Andy Henning, Senior Building and Construction Projects Manager
Recommended Action
Approve
Analysis
On December 13, 2016 the City Council awarded the Construction Manager at Risk (CMAR) contract to Modern Contractors for pre-construction services in the amount of $1,000. This award provided for CMAR services including development of project estimates, preliminary construction schedules, value engineering proposals and constructability review during the Design Phase.
The current Change Order/Amendment No. 7 in the amount of $28,953.39 is divided as follows:
1. $4,365 for extension of spiral ductwork vs. standard ductwork due to designation clarification
2. $8,337 for ductwork extension into restrooms to provide air-conditioned space
3. $2,835 for natural gas piping required to connect to replacement roof top mechanical units
4. $9,668 for site grading changes required to coordinate with phase two work removed
5. $1,039 for demolition in room 110 due to unforeseen condition previously hidden
6. $6,204 for wood furring required at service bay overhead doors to coordinate with wall insulation thickness and door track/motor positioning
7. $5,262 for added energy code requirements per inspection review
8. $407 for grouting of existing door frame where necessary reinforcement was missing
9. $850 for GFCI receptacles (waterproof vs. water-resistant) in shop area per electrical inspector review and code requirement
10. $6,975 for additional air hose ...