Skip to main content
File #: 14-4010    Version: 1 Name: Generators-Cancel and Award Bid
Type: Agenda Item Status: Consent Agenda
File created: 8/22/2014 In control: Facility Services
On agenda: 9/2/2014 Final action: 9/2/2014
Title: Cancel purchase awarded by Council on March 4, 2014, File #14-3454 to Holt Caterpillar Power Systems for purchase and turnkey installation of six (6) generators for a total of $553,968 and award the purchase and turnkey installation of five (5) generators from Holt Caterpillar Power Systems at the Main Library, Fire Stations #2 and # 8, Service Center, and Tony Shotwell Life Center for $541,339, and the purchase of fuel for generators from Martin Eagle Oil at current price estimate for $5,891 for a total cost of $547,230
Attachments: 1. 14-4010 Generators-FS2-FS8-MLIB-SCNTR-SHTWL .pdf, 2. CC 14-4010 FIS-Generator-Install FS 2 and 8 09-02-2014.pdf, 3. CC 14-4010 FIS-Generator-Install Main Lib 09-02-2014.pdf, 4. CC 14-4010 FIS-Generator-Install Serv Center and Shotwell Center 09-02-2014.pdf, 5. CC 14-4010 FIS-Generator-Install Shotwell Cntr-2.pdf, 6. CC 14-4010 FIS-Generator-Install Shotwell Cntr-3.pdf
From
Ray Riedinger

Title
Cancel purchase awarded by Council on March 4, 2014, File #14-3454 to Holt Caterpillar Power Systems for purchase and turnkey installation of six (6) generators for a total of $553,968 and award the purchase and turnkey installation of five (5) generators from Holt Caterpillar Power Systems at the Main Library, Fire Stations #2 and # 8, Service Center, and Tony Shotwell Life Center for $541,339, and the purchase of fuel for generators from Martin Eagle Oil at current price estimate for $5,891 for a total cost of $547,230

Presenter
Diana Ortiz, CFO

Recommended Action
Approve

Analysis
On March 4, 2014 Council awarded the purchase and installation of six (6) generators to Holt Caterpillar Power Systems in the amount of $553,968, for the following locations: Main Library, Fire Stations 2 and 8, Service Center, Tony Shotwell Life Center and Charley Taylor Recreation Center.The City's facility maintenance program includes replacement/installment of generators necessary for ongoing, seamless operations, specifically for Information Technology systems, power outages, and storm shelters. The annual capital project plan for new/improved municipal facilities scheduled and budgeted for generators include Main Library, Fire Station 2, Fire Station 8, and Service Center. The Tony Shotwell Life Center has not been equipped with a generator.

All generators previously approved for purchase were sized based on current electrical loading. Greater use of the facilities, thus increased electrical loads, at the Tony Shotwell Life Center, the Service Center and the Main Library require larger generators and specifications have been resubmitted. Future renovations at Charley Taylor Recreation Center are in the planning stages; therefore, the generator for this site will be cancelled and it will be rebid when project plans are closer to a final phase and the appropriate electrical load determined.

The Main Library hosts technology equipment whic...