File #: 19-8829    Version: 1 Name: Ordinance amending the FY 2018/2019 Capital Improvement Projects Budget; Construction contract with Gra Tex Utilities, Inc. in the amount of $314,097.50 for Fire Station #3 Waterline Relocation; Material testing with Alliance Geotechnical Group in the amo
Type: Ordinance Status: Adopted
File created: 3/25/2019 In control: Engineering
On agenda: 4/2/2019 Final action: 4/2/2019
Title: Ordinance amending the FY 2018/2019 Capital Improvement Projects Budget; Construction contract with Gra-Tex Utilities, Inc. in the amount of $314,097.60 for Fire Station #3 Waterline Relocation; Material testing with Alliance Geotechnical Group in the amount of $3,819.75; In-house labor distribution in the amount of $15,705; 5% contract contingency in the amount of $15,705; for a total project cost of $349,327.35
Attachments: 1. 19-8829 618.113 FS3 WL
From
max

Title
Ordinance amending the FY 2018/2019 Capital Improvement Projects Budget; Construction contract with Gra-Tex Utilities, Inc. in the amount of $314,097.60 for Fire Station #3 Waterline Relocation; Material testing with Alliance Geotechnical Group in the amount of $3,819.75; In-house labor distribution in the amount of $15,705; 5% contract contingency in the amount of $15,705; for a total project cost of $349,327.35

Presenter
Gabe Johnson, Director of Public Works and Romin Khavari, City Engineer

Recommended Action
Approve

Analysis
This waterline relocation contract will provide utility clearances for proposed fire station No.3 site at Marshall Drive between Robinson Rd and SH 161. This project includes 819 linear feet of 24” and 16” PVC water main by open-cut and other related items of work.

The City of Grand Prairie advertised and received a total of eight (8) bids for this project on Tuesday, March 5, 2019 as follows:

Gra-Tex Utilities, Inc. Total Bid: $314,097.50
Atkins Brothers Total Bid: $337,401.00
La Banda LLC Total Bid: $346,530.50
SYB Construction Total Bid: $349,204.00
Saber Development Total Bid: $357,411.50
Flow line Construction Total Bid: $359,367.00
Flow line Utilities Total Bid: $361,304.00
Aushill Construction Total Bid: $398,223.00

Staff recommends this project be awarded to Gra-Tex Utilities in the amount of $314,097.50

Project is anticipated to begin in April 2019 with projected completion by July 2019.

Financial Consideration
Funding for a construction contract with Gra-Tex Utilities, Inc. in the amount of $314,098 for Fire Station #3 Waterline Relocation; Material testing with Alliance Geotechnical Group in the amount of $3,820; In-house labor distribution in the amount of $15,705; 5% contract contingency in the amount of $15,705; for a total project cost of $349,328, is available by approving an ordinance transferring and appropriating from the unobligated fund b...