Skip to main content
File #: 18-8073    Version: 1 Name: Warmack Library Change Order/Amendment No. 2 with Pogue Construction in the amount of $94,388.97 for helical piles, HVAC equipment change, curtain wall revisions, structural grade beam adjustments, decorative panel color change and increase of glazing sol
Type: Agenda Item Status: Consent Agenda
File created: 7/20/2018 In control: Engineering
On agenda: 8/7/2018 Final action: 8/7/2018
Title: Warmack Library Change Order/Amendment No. 2 with Pogue Construction in the amount of $94,388.97 for helical piles, HVAC equipment change, curtain wall revisions, structural grade beam adjustments, decorative panel color change and increase of glazing solar screening
Attachments: 1. 18-8073 Warmack 617.17.pdf
From
max

Title
Warmack Library Change Order/Amendment No. 2 with Pogue Construction in the amount of $94,388.97 for helical piles, HVAC equipment change, curtain wall revisions, structural grade beam adjustments, decorative panel color change and increase of glazing solar screening

Presenter
Andy Henning, Senior Building and Construction Projects Manager

Recommended Action
Approve

Analysis
On August 15, 2017 the City Council awarded the Construction Manager at Risk (CMAR) contract to Pogue Construction for pre-construction services in the amount of $7,500. This award provided for CMAR services including development of project estimates, preliminary construction schedules, value engineering proposals and constructability review during the Design Phase.

The current Change Order/Amendment No. 2 in the amount of $94,388.97 is divided as follows:
$41,778.00 for structural concrete bell pier replacement with steel helical piles in areas where below grade sand pockets were encountered associated with the west adult programming addition
$18,285.91 for Trane HVAC equipment change
$14,173.94 for increased curtain wall depth to meet structural wind loading criteria at all tall glazing locations
$8,695.09 for necessary structural concrete grade beam revisions as required to coordinate with the introduction of the steel helical piles at the west adult programming addition
$1,005.26 for 3 form panel color change associated with designed art installation
$10,450.77 for change from 60 to 70xl solar ban low-e coating for purposes of achieving requirements of the energy code

Change Order/Amendment No. 1 in the amount of $4,498,830 was approved by City Council on January 9, 2018 (18-7947) for the Guaranteed Maximum Price (GMP) for the scope of work defined in the Komatsu Architects Construction Documents package as competitively bid by Subcontractors to Pogue Construction. Costs above and beyond the Pogue Construction portion of the project addressed in the Change ...

Click here for full text