Legislation Details

File #: 20-10316    Version: 1 Name: Change Order #6 to Construction contract with Axis Contracting, Inc.for Intersection Improvements at three locations
Type: Agenda Item Status: Consent Agenda
File created: 8/21/2020 In control: Engineering
On agenda: 9/1/2020 Final action: 9/1/2020
Title: Change Order/Amendment No. 6 in the net amount of $14,116 with Axis Contracting, Inc. for Intersection Improvements at three locations (Lone Star Parkway/S. Belt Line Road, Great Southwest Parkway/Lake Ridge Parkway, and Jefferson Street/ South Carrier Parkway intersections)
Attachments: 1. WO 620.70.pdf
From
max

Title
Change Order/Amendment No. 6 in the net amount of $14,116 with Axis Contracting, Inc. for Intersection Improvements at three locations (Lone Star Parkway/S. Belt Line Road, Great Southwest Parkway/Lake Ridge Parkway, and Jefferson Street/ South Carrier Parkway intersections)

Presenter
Walter Shumac, Director of Transportation, and Romin Khavari, City Engineer

Recommended Action
Approve

Analysis
On December 17, 2019 City Council Approved a construction Contract with Axis Contracting, Inc. in the amount of $1,252,354 for Intersection Improvements at three locations; Material testing with Team Consultants in the amount of $28,275; 5% contingency in the amount of $62,618; In-house labor distribution in the amount of $62,618 for a total project cost of $1,405,865.

This project provides for paving, sidewalks, barrier free ramps, traffic signals and drainage improvements at Lone Star Parkway/S. Belt Line Road, Great Southwest Parkway/Lake Ridge Parkway, and Jefferson Street/ South Carrier Parkway intersections.

Proposed Change order/Amendment No. 6 provides for Traffic signal/ PED pole modifications at Carrier Parkway/Jefferson Street intersection for a total amount of $14,116

Change order/Amendment No. 5 in the amount of $5,750 provided for 3” electrical conduit repairs in Carrier Parkway south of Jefferson.

Change order/Amendment No. 4 approved by Council July 15, 2020 provided for Traffic signal modifications at south Carrier Parkway/Jefferson Street intersection for a total increase of $11,142 and a total decrease of $3,315 for a net total increase of $7,827.

Change order/Amendment No. 3 in the amount of $41,580 provided for Storm drain modifications due to conflicts at South Carrier Pkwy/ Jefferson St. intersections.

Change order/Amendment No. 2 in the amount of $4,275 provided for Electrical Wire adjustments at Great Southwest Pkwy/ Lakeridge Pkwy Intersection.

Change order/Amendment No. 1 was voided under C.O 3 due to a ...

Click here for full text