Change Order/Amendment No. 6 in the net amount of $14,116 with Axis Contracting, Inc. for Intersection Improvements at three locations (Lone Star Parkway/S. Belt Line Road, Great Southwest Parkway/Lake Ridge Parkway, and Jefferson Street/ South Carrier Parkway intersections)
Presenter
Walter Shumac, Director of Transportation, and Romin Khavari, City Engineer
Recommended Action
Approve
Analysis
On December 17, 2019 City Council Approved a construction Contract with Axis Contracting, Inc. in the amount of $1,252,354 for Intersection Improvements at three locations; Material testing with Team Consultants in the amount of $28,275; 5% contingency in the amount of $62,618; In-house labor distribution in the amount of $62,618 for a total project cost of $1,405,865.
This project provides for paving, sidewalks, barrier free ramps, traffic signals and drainage improvements at Lone Star Parkway/S. Belt Line Road, Great Southwest Parkway/Lake Ridge Parkway, and Jefferson Street/ South Carrier Parkway intersections.
Proposed Change order/Amendment No. 6 provides for Traffic signal/ PED pole modifications at Carrier Parkway/Jefferson Street intersection for a total amount of $14,116
Change order/Amendment No. 5 in the amount of $5,750 provided for 3” electrical conduit repairs in Carrier Parkway south of Jefferson.
Change order/Amendment No. 4 approved by Council July 15, 2020 provided for Traffic signal modifications at south Carrier Parkway/Jefferson Street intersection for a total increase of $11,142 and a total decrease of $3,315 for a net total increase of $7,827.
Change order/Amendment No. 3 in the amount of $41,580 provided for Storm drain modifications due to conflicts at South Carrier Pkwy/ Jefferson St. intersections.
Change order/Amendment No. 2 in the amount of $4,275 provided for Electrical Wire adjustments at Great Southwest Pkwy/ Lakeridge Pkwy Intersection.
Change order/Amendment No. 1 was voided under C.O 3 due to a ...