Title: Ordinance amending the FY 2015/2016 Capital Improvements Projects Budget; change order No. 3 with SYB Construction in the amount of $9,049 for wastewater replacements at various locations throughout the city
Attachments: 1. 16-5413 SYB.pdf
From
max

Title
Ordinance amending the FY 2015/2016 Capital Improvements Projects Budget; change order No. 3 with SYB Construction in the amount of $9,049 for wastewater replacements at various locations throughout the city

Presenter
Ron McCuller, Director of Public Works and Romin Khavari, City Engineer

Recommended Action
Approve

Analysis
On May 19, 2015, the City of Grand Prairie awarded a construction contract to SYB Construction in the amount of $548,527.70 and approved a 5% contingency of $27,426.00 for a total of $575,953.70 for the wastewater replacements construction project.

On October 13, 2015, the City awarded a change order/amendment No. 2 for the FY 2012/2013 wastewater replacements construction project in the amount of $66,590 to SYB Construction for additional construction costs at the Marshall Drive/Belt Line Road. location. These additional costs were due to the re-design and subsequent lowering of the proposed wastewater line because of unforeseen existing utility conflicts encountered by SYB Construction during construction at this location.

SYB Construction has now completed work at five of the six locations included in this construction contract. Change order/amendment No. 3 in the amount of $9,049 provides for the following:

- An additional $3,429 for additional pavement repairs at the NW 23rd/NW 24th Street location
- An additional $12,560 for the addition of a four foot diameter wastewater manhole and additional pavement repairs on Marshall Drive.
- A credit of $6,940 for the removal of a five foot diameter wastewater manhole at this location

Change order/amendment No. 1 was in the net amount of $16,879.00 for addition and deletion of items based upon different conditions encountered during the course of construction at the Austrian Way, Graham Street, Dallas Street, NW 23rd Street, and Marshall Drive.

Change order/amendment No. 2 was in the net amount of $66,590.00 for additional construction costs due to the re-desig...