From
Lee Harriss
Title
Contract with Exterior Appeal for Brick Wall Repairs in the amount of $139,118.75 - Peninsula PID (Council Districts 4 and 6)
Presenter
Lee Harriss, Special District Administrator
Recommended Action
Approve
Analysis
The PID Board recommended that a contract for brick wall repairs be awarded to Exterior Appeal. The walls to be repaired are located throughout Peninsula PID.
Texas Local Government Code, Chapter 252.022 (a) (9) exempts public improvement districts from competitive bidding requirements. Per that statute, the PID Advisory Board is empowered to enter into contracts such as the one with Exterior Appeal following approval by the City Council.
Financial Consideration
Funds for this contract are available from annual assessments adopted by the City Council on September 20, 2016, which are estimated to generate $1,149,063 for the fiscal year.