Ordinance amending the FY 2018/2019 Capital Improvement Projects Budget; Construction Change Order/Amendment No. 1 Gra-Tex Utilities, Inc. in the amount of $62,842.50 for Fire Station #3 Waterline Relocation
Presenter
Gabe Johnson, Director of Public Works
Recommended Action
Approve
Analysis
On April 2, 2019, the City of Grand Prairie awarded a construction contract in the amount of $314,097.50 to Gra-Tex Utilities, Inc. for the waterline relocation to provide utility clearances for proposed fire station No.3 site at Marshall Drive between Robinson Rd and SH 161. This project included 819 linear feet of 24” and 16” PVC water main by open-cut and other related items of work.
The original design was based on an assumed connection point established prior to beginning the design of the Robin Road Pump Station. The connection point changed during the Preliminary Design Report which caused these relocations to be adjusted in order to avoid having unnecessary piping once the future Pump Station became operational. The current Change Order/Amendment No. 1 eliminates unnecessary piping that would have been left unused once the future Robinson Road Pump Station comes online in 2022. This Change Order represents approximately a 20% increase.
The completion date will be revised until the end of September 2019.
Financial Consideration
Funding in the total amount of $62,843 is available as follows:
1. $5,705 is available in the Water Capital Projects Fund (500592) WO #01811303 (Robinson Rd EST & 30" Water Line) Contract 354791 Contingency line 2
2. $57,138 is available by approving an ordinance transferring and appropriating from the unobligated fund balance in the Water Capital Projects Fund (500592), to WO #01811303 (Robinson Rd EST & 30" Water Line)
Body
AN ORDINANCE OF THE CITY OF GRAND PRAIRIE, TEXAS, AMENDING THE FY 2018/2019 CAPITAL IMPROVEMENT PROJECTS BUDGET BY TRANSFERRING AND APPROPRIATING $57,138 FROM THE UNOBLIGATED FUND BALANC...
Click here for full text