File #: 17-6363    Version: 1 Name: Change Order No. 2 Construction contract with McMahon Contracting, Inc. for Oakdale Paving and Drainage Improvements
Type: Agenda Item Status: Consent Agenda
File created: 12/29/2016 In control: Engineering
On agenda: 1/10/2017 Final action: 1/10/2017
Title: Change Order No. 2 for the construction contract with McMahon Contracting, Inc. in the net negative amount of -$14,378.14 for Oakdale Paving and Drainage Improvements
Attachments: 1. 17-6363 Oakdale co 2 STRT.pdf, 2. 17-6363 Oakdale co2 WTER
From
max

Title
Change Order No. 2 for the construction contract with McMahon Contracting, Inc. in the net negative amount of -$14,378.14 for Oakdale Paving and Drainage Improvements

Presenter
Romin Khavari, City Engineer and Ron McCuller, Public Works Director

Recommended Action
Approve

Analysis
On August 2, 2016 the City Council (16-5861) approved a construction contract with McMahon Contracting, Inc. in the amount of $1,677,641.72 for Oakdale Paving and Drainage Improvements; 5% construction contingency in the amount of $83,882; material testing with Team Consultants in the amount of $20,910.75; in-house engineering in the amount of $65,428.03; street lighting improvements in the amount of $15,000 for a total project cost of $1,862,862.50.

This project provides for paving and drainage improvements for Phase I of Oakdale Road between Roy Orr Blvd to the existing dogleg at Old Oakdale Road. Phase I of the Oakdale project consists of 600 feet of concrete 4-lane divided thoroughfare between Roy Orr Blvd and the dogleg at Old Oakdale Rd; it also provides for the installation of traffic signals at the intersection of Oakdale Road and Roy Orr Blvd., storm drain and water main improvements, street lighting and other related items of work.
Phase II segment of Oakdale Road Project provided for 30% design and will extend Oakdale Road 3000 feet eastward to SH 161; design of this segment will be completed and constructed under separate contracts in FY 2021 and beyond and pending future developments in the area. The project cost proposal was over its allocated budget, FNI worked with the City to eliminate the storm drainage work from the Phase II portion of the project since the interim measures completed by City crews earlier this year appear to have solved the immediate ponding drainage concern at that location. The drainage improvements will be included in the overall Oakdale Phase II construction at a future date.

Change Order/Amendment No. 1 in the net ...