Legislation Details

File #: 20-10706    Version: 1 Name: Resolution; Professional Engineering Services contract with Criado and Associates for Dechman Drive
Type: Resolution Status: Adopted
File created: 12/21/2020 In control: Engineering
On agenda: 1/5/2021 Final action: 1/5/2021
Title: Resolution declaring expectation to reimburse expenditures with proceeds of future debt in the amount of $48,500 for Professional Engineering Services contract with Criado and Associates for Dechman Drive from Westchester Parkway to Bardin Road; Authorize City Manager to enter into Professional Engineering Services Contract with Criado and Associates
Attachments: 1. 05-11-2020 ULine 332.21.pdf, 2. W.O. 621.59.pdf
From
max

Title
Resolution declaring expectation to reimburse expenditures with proceeds of future debt in the amount of $48,500 for Professional Engineering Services contract with Criado and Associates for Dechman Drive from Westchester Parkway to Bardin Road; Authorize City Manager to enter into Professional Engineering Services Contract with Criado and Associates

Presenter
Gabe Johnson, Director of Public Works, Walter Shumac, Director of Transportation and Romin Khavari, City Engineer

Recommended Action
Approve

Analysis
As part of the FY 2020/2021 Capital Improvement Projects (CIP) budget, funds were approved to design the extension of an unimproved section of Dechman Drive from Westchester Parkway to Edgeview Drive to connect to Bardin Road. The approximate 780-foot roadway section is to be constructed as a 45-foot back-to-back minor arterial concrete street section with a 4-foot sidewalk along the west side of the road to include, drainage, 12” waterline, Irrigation and landscaping along the west side of the street to match up with the northern connection section to be included as part of the project.

The City requested qualification statements from seven (7) firms and the selection committee selected Criado and Associates to turn in a priced proposal for the design of this project.

Due to the flat area, the project is to be designed in two phases. The current contract for Phase I will include preparing 30% Engineering design plans based on field surveying, Geotechnical, and Subsurface Utility Engineering and to include preparing preliminary plans for the roadway to include defining the drainage patterns and outfall as well as need for retaining walls, etc. based on field conditions.

The final design (Phase II) will include the preparation of the final paving, drainage, 12” waterline plans to include irrigation, landscaping and sidewalk along the west side of the roadway.

The City is also discussing these proposed improvements with the ...