File #: 17-7106    Version: 1 Name: Change Order/Amendment No. 1 with Hill & Wilkinson General Contractors for Shotwell Library Renovations
Type: Agenda Item Status: Consent Agenda
File created: 8/25/2017 In control: Engineering
On agenda: 9/5/2017 Final action: 9/5/2017
Title: Change Order/Amendment No. 1 with Hill & Wilkinson General Contractors in the amount of $460,573 for the balance of the construction cost for the renovations to Shotwell Library; 5% contingency in the amount of $23,029; allowance of $10,000 for data wiring and IT switching; $15,000 allowance for exterior lighting for signage; $7,500 allowance for moving and storage of existing library equipment and the overall library collection; plus an $18,000 additional furniture, fixture and equipment (FF&E) budget allowance for a total funding request in the amount of $534,102.
Attachments: 1. 17-7106 Shotwell Library.pdf
From
max

Title
Change Order/Amendment No. 1 with Hill & Wilkinson General Contractors in the amount of $460,573 for the balance of the construction cost for the renovations to Shotwell Library; 5% contingency in the amount of $23,029; allowance of $10,000 for data wiring and IT switching; $15,000 allowance for exterior lighting for signage; $7,500 allowance for moving and storage of existing library equipment and the overall library collection; plus an $18,000 additional furniture, fixture and equipment (FF&E) budget allowance for a total funding request in the amount of $534,102.

Presenter
Andy Henning, Senior Building and Construction Projects Manager

Recommended Action
Approve

Analysis
On December 13, 2016 the City Council awarded the Construction Manager at Risk (CMAR) contract to Hill & Wilkinson General Contractors for pre-construction services in the amount of $7,500. This award addressed CMAR services including development of project estimates, preliminary construction schedules, value engineering services and constructability review during the Design Phase.

The current Change Order/Amendment No. 1 in the amount of $460,573 represents the Guaranteed Maximum Price (GMP) for the scope of work currently defined in the 720 Design Architects Construction Documents Package as competitively bid by Subcontractors to Hill & Wilkinson General Contractors. Items applicable to performance by the Construction Manager at Risk (CMAR) will be incorporated into the current Hill & Wilkinson General Contractors contract for a revised total contract in the amount of $468, 073.

Additional project costs requested above and beyond the current change order/amendment No. 1 with Hill & Wilkinson General Contractors portion of the project include the following:
1) 5% contingency in the amount of $23,029
2) $10,000 allowance for data wiring and IT switching
3) $15,000 allowance for exterior lighting for signage
4) $7,500 allowance for moving and storage of existing l...