From
max
Title
Change Order/Amendment No. 6 with Lee Lewis Construction, Inc. in the amount of $81,269 for the added street and water modifications at Arkansas Lane for the EPIC in Grand Central Park
Presenter
Tom Cox, Deputy City Manager
Recommended Action
Approve
Analysis
On December 9, 2014 the City Council awarded the Construction Manager at Risk (CMAR) contract to Lee Lewis Construction, Inc. for pre-construction services in the amount of $20,000. This award provided the CMAR services including development of project estimates, preliminary construction schedules, value engineering and constructability review during the Design Phase.
The current Change Order/Amendment No. 6 in the amount of $81,269 is divided as follows: 1. $52,174 is for the added bore at Arkansas Lane and the adjustment at the AT&T conduit lines, Oncor duct bank and re-mobilization. 2. $19,685 for installation of a line stop on the 8" waterline and the cut in of the gate value at the PSB 3. $9,410 for a 13'5" deeper connection on the 16" waterline connection in Arkansas Lane
Change Order/Amendment No. 1 in the amount of $1,100,000 was approved by City Council on November 3, 2015 (15-5108) allowing for the pre-purchase of aluminum materials that would be utilized in the construction of the OpenAire retractable roof system for the EPIC Waters portion of the project.
Change Order/Amendment No. 2 in the amount of $6,794,652.49 was approved by City Council on March 3, 2016 to get early phase construction activities underway. The elements included in Change Order No. 2 covered the direct subcontract costs for dirt and site work ($2,217,205.10), underground site utilities installation work ($2,253,997.20), design and fabrication of confirmed water park feature rides to allow for their timely installation ($1,412,117.40), and associated CMAR costs for General Conditions ($650,000) and Insurance and Fees ($261,332.79) for a total approved amount of $6,794,652.49.
Change Order/Amen...
Click here for full text