File #: 18-8127    Version: 1 Name: Final Reconciliation Amendment/Change Order No. 2 with TNT Farms and Landscaping for Johnson Creek Channel Repairs
Type: Agenda Item Status: Consent Agenda
File created: 7/27/2018 In control: Engineering
On agenda: 8/7/2018 Final action: 8/7/2018
Title: Final Reconciliation Amendment/Change Order No. 2 with TNT Farms and Landscaping for Johnson Creek Channel Repairs in the net negative amount of $296.58
Attachments: 1. 18-8127 Johnson Crk 618.pdf

From

max

 

Title

Final Reconciliation Amendment/Change Order No. 2 with TNT Farms and Landscaping for Johnson Creek Channel Repairs in the net negative amount of $296.58

 

Presenter

Gabriel Johnson, Director of Public Works.

 

Recommended Action

Approve

 

Analysis

On May 1, 2018, (18-7793) the City of Grand Prairie council approved a construction contract with TNT Farms and Landscaping in the amount of $395,490 for the Johnson Creek Channel Floor Repair.

 

The current Amendment/Change Order No. 2 allows for final reconciliation of all items based on final inspection and measurements resulting in the net negative amount of $296.58. (decrease amount of $18,915.00; increase amount of $18,618.42)

 

Amendment/change order No.1 approved by the City  on July 12, 2018 in the amount $24,970 allowed for additional site preparation, construction staking, water management, grouted rock riprap with geotextile.

 

State statutes require City Council approval of change orders when the cumulative cost exceeds $50,000. The project is complete however the cumulative amount of Amendment/Change Order No. 1 in the amount of $24,970 and the current Amendment/Change Order No. 2 amount of $37,533.42 totals $62,503.42 which requires council approval.

 

Total Project cost: $420,163.42

 

Financial Consideration

No additional funding required for this final reconciliation amendment/change order No. 2, project funding is in the Storm Drainage Capital Projects Fund (401592) WO #01806503 (FY18 Misc Drainage Improvements)