File #: 19-8529    Version: 1 Name: Professional Engineering Services contract with Freese and Nichols, Inc. for the Robinson Road Pump Station and Elevated Storage Tank in the amount of $1,695,000
Type: Ordinance Status: Adopted
File created: 12/18/2018 In control: Engineering
On agenda: 1/8/2019 Final action: 1/8/2019
Title: Professional Engineering Services contract with Freese and Nichols, Inc. for the Robinson Road Pump Station and Elevated Storage Tank in the amount of $1,695,000
Attachments: 1. Scope of Services.pdf, 2. 619.106.pdf

From

max

 

Title

Professional Engineering Services contract with Freese and Nichols, Inc. for the Robinson Road Pump Station and Elevated Storage Tank in the amount of $1,695,000

 

Presenter

Gabe Johnson, Director of Public Works

 

Recommended Action

Approve

 

Analysis

The Robinson Road Pump Station and Elevated Storage Tank was identified as part of the FY 19 Capital Projects Budget and Capital Projects Plan for proposed water projects. 

 

The professional engineering contract will include:

                     - Robinson Road 12 MGD Pump Station

                                          Design of Pump Station and appurtenances to house four (4) new horizontal split case pumps and motors to deliver a firm capacity of 12 MGD and associated yard piping required to connect the proposed Pump Station to the existing system

                                          Bid Phase Services

                                          General Representation Construction Phase Services

 

                     - Robinson Road 2 MG Composite Elevated Storage Tank

                                          Design of Composite Elevated Storage Tank and appurtenances

                                          Chemical Storage Tanks and Pads for Residual Boosting

                                          Design of an Active Mixing System

 

                     - Demolition of Site Facilities

                                          Existing Fire Station to include asbestos sampling

                                          Existing elevated Storage Tank to include Heavy Metals Paint sampling

                                          Existing Fire Tower and assoicated training equipment

                                          Existing Elevated Storage tank as part ofelevated Storage Tank construciton package

 

                     - Subconsultant work for lead and asbestos sampling, survey, drilling and testing.

 

Design of this project is scheduled to begin in January 2019 with an estimated completion time around the end of September 2020.

 

This item was presented to the Finance and Government Committee on January 8, 2019.

 

Financial Consideration

Funding in the total amount of $1,695,000 is available in Water Capital Projects Budget (500592) W.O.#01910603 (2N-2.0 MG Robinson Road EST and 12 MGD Pump Station.)