File #: 10-0661    Version: 1 Name: Drainage Improvements Change Order 1 with Texas Standard
Type: Agenda Item Status: Passed
File created: 10/18/2010 In control: Engineering
On agenda: 11/2/2010 Final action: 11/2/2010
Title: Change Order No. 1 with Texas Standard in the amount of $19,287.50 for Drainage Improvements at various locations
Attachments: 1. Fiscal Impact Statement 591.pdf, 2. Fiscal Impact Statement 610.pdf
From
Max

Title
Change Order No. 1 with Texas Standard in the amount of $19,287.50 for Drainage Improvements at various locations

Presenter
Romin Khavari, City Engineer

Recommend Action
Approve

Analysis
On July 6th, 2010, a construction contract was awarded to Texas Standard Construction in the amount of $267,598 for construction of the Drainage Improvements at various locations.

This project provides for improvements at four locations:
Erosion Control Repair Behind 3718 & 3722 Bluegrass Drive ($21,563)
Drainage Improvements Behind 2972 Pinehurst Lane ($50,532)
Channel Improvements at 844 & 848 Bentwater Parkway ($46,015)
Lakeview Drainage Improvements ($149,488)


The proposed change order No.1 is to provide for the following additional work:
1. During the construction of the drainage improvements behind 2972 Pinehurst Lane, it was discovered that the pipe joints of the existing 60" diameter reinforced concrete drainage outfall pipe have separated. This Change Order provides for filling the 14 pipe joint gaps with concrete grout and wiping the joints smooth for the cost of $2,450.

2. During the construction of the channel improvements at 844 & 848 Bentwater Parkway a water service was encountered which required relocation. This Change Order provides for
relocating the water service to clear the channel improvements for the cost of $500.

3. Addition of another location to this project. The construction of Webb Lynn Road from south of Lantern Way to south of Heather Drive constructed by the Developer in 2003 failed to provide a drainage outfall for the property at 8018 Webb Lynn Road. This Change Order provides two concrete flumes to drain the property for the cost of $16,337.50.

The grand total amount for the proposed Change Order No. 1 is $19,287.50. Fourteen additional days has been requested for this work.

Financial Consideration
State statutes require City Council approval of a change order when the cumulative cost of this change order ...

Click here for full text