Skip to main content
File #: 17-6951    Version: 1 Name: Ordinance; Construction Contract for Central Park Irrigation Well
Type: Ordinance Status: Adopted
File created: 7/11/2017 In control: Public Works
On agenda: 8/1/2017 Final action: 8/1/2017
Title: Ordinance amending the FY 2016/2017 Capital Improvement Projects Budget and the Park Venue Fund; Construction contract to Layne in the base bid amount of $1,198,814.00 and add alternate #2 in the amount of $84,329.00 for a total construction contract amount of $1,283,143.00 for the construction of an irrigation well at Central Park; Material testing with Alliance Geotechnical Group in the amount of $6,040; 5% contract contingency in the amount of $64,157; In-house engineering in the amount of $64,157 for a total project cost of $1,417,497.00
Attachments: 1. 17-6951 Park Water Well, 2. FS Park Venue 2018
From
max

Title
Ordinance amending the FY 2016/2017 Capital Improvement Projects Budget and the Park Venue Fund; Construction contract to Layne in the base bid amount of $1,198,814.00 and add alternate #2 in the amount of $84,329.00 for a total construction contract amount of $1,283,143.00 for the construction of an irrigation well at Central Park; Material testing with Alliance Geotechnical Group in the amount of $6,040; 5% contract contingency in the amount of $64,157; In-house engineering in the amount of $64,157 for a total project cost of $1,417,497.00

Presenter
Ron McCuller, Director of Public Works

Recommended Action
Approve

Analysis
The Lakes at Central Park with the help of a relatively low production water well have been unable to keep up with the demands of evaporation and irrigation so that the water falls remain active. A deeper more productive well is in order to address this issue.

The engineering firm of Freese & Nichols has completed plans and specifications for a new well to address this need. On august 1, 2017 a total of one bid was received for this project from Layne as follows:
Contractor Base Bid Add Alt No.1 Add Alt No. 2
Layne $1,198,814.00 $42,165.00 $84,329.00

Layne has previously done projects for the the City and is highly skilled in water wells.

This item was presented to the Finance and Government Committee on August 1, 2017 and the City Council Development Committee on July 14, 2017.

Construction of this project is scheduled to start the second week of August 2017 with completion in mid November 2017.

Staff recommends the construction of awarding $1,198,814 base bid and add alternate No. 2 in the amount of $84,329. Add alternate No. 2 is to provide sound walls around the project site to reduce the noise levels during well drilling operation.

Financial Consideration
Funding for the construction of the water well in the amount of $1, 417,497.00 is available as follows:

1. $442,528 is available by approving ...