Ordinance amending the FY 2014/2015 Capital Improvement Projects Budget; Amendment 3 to the KSA contract to design additional parking and electrical improvements in the terminal area for $7,750 for unanticipated expenses associated with the need to rebid the project; Amendment 4 to the KSA contract to parking and design electrical improvements in the terminal area for $91,420.00 for project management; Award of Contract to Mart, Inc. for $729,048.48 for a total amount $828,218.48 (Bid # 15138); and Reject Bid 15116.
Presenter
Randy J. Byers, C.M., Airport Director
Recommended Action
Approve
Analysis
On May 20, 2014, the Grand Prairie City Council approved a contract with KSA Engineers for the design of electrical improvements in the amount of $37,500. As KSA began reviewing the terminal area, they suggested that all the improvements planned for the area be included in one design document to avoid potential conflicts in the design elements of the future improvements. On July 15, 2014, the Grand Prairie City Council approved an amendment to the contract with KSA Engineers for the design of electrical improvements in the amount of $37,680 for a total of
Notice of bid #15138 was advertised and 34 vendors viewed the advertisement on BidSync. One bid was received on June 25, 2015. The sole bidder for the project was Mart, Inc. as follows:
Section I - Parking Expansion (Asphalt Paving) $ 323,809.25
Section I - Additive Alternate No. 1 (Concrete Paving) 53,043.16
Section II - North Grading Adjustments 6,164.65
Section III - Electrical Improvements 353,781.42
Fee for Rebid - 7,750.00
$ 729,048.48
KSA Engineers, Inc., have submitted Change Order Number 3 for $7,750 to cover the costs associated with preparing the project documents for a second bid and their staff time to print and distribute the documents. Mart, Inc. has agreed to the stipulation of reducing their contract by $7,750, the fee for the rebid o...