File #: 14-4033    Version: 1 Name: Reject Bids for Central Park Repairs, Y#0980
Type: Agenda Item Status: Consent Agenda
File created: 9/2/2014 In control: Engineering
On agenda: 9/16/2014 Final action: 9/16/2014
Title: Reject bids for Central Park Repairs, Y#0980
Attachments: 1. Central Park Repairs Exhibit, 2. L140826CentralParkRepairs
From
max

Title
Reject bids for Central Park Repairs, Y#0980

Presenter
Bill Crolley, Director of Planning and Development and Romin Khavari, City Engineer

Recommended Action
Approve

Analysis
Halff Associates was hired to design improvements to remedy soil movement along the pedestrian brides at the Summit and two entrances to the Summit and two entrances to the Public Safety Building, to include erosion concerns along the existing warrior creek and lakes 1 and 2. Halff Associates designed improvements for the following items of work bid as Base Bid and five Alternate Bids, also shown on the attached exhibit:

Base Bid:
1. Repair two pedestrian bridges in front of the Summit due to soil movement to include removal and replacement of approximately 134 Square Yards of sidewalk, 820 Cubic Yards of rock riprap installation and miscellaneous related items of work.
2. Flatwork repairs to the Summit front and rear entrances due to soil movement to include approximately 237 Square yards of flatwork removal and replacement with modified flatwork pavement and miscellaneous related items of work.
3. Flatwork repairs to the Public Safety Building at the jail and east side entrances due to soil movement to include approximately 1,320 Square feet of brick pavers, 117 Square yards of flatwork removal and replacement with modified flatwork pavement and miscellaneous related items of work.

Alternate No. 1 Bid: Warrior creek erosion improvements to primarily include installation of approximately 355 Cubic Yards of rock rip-rap and miscellaneous related items of work.

Alternate No. 2 Bid: Landscape Repairs for Lake 1 to include approximately 14,665 Square feet of top soil, seed mix to include temporary irrigation and miscellaneous related items of work.

Alternate No. 3 Bid: Landscape Repairs for Lake 2 to include approximately 44,955 Square feet of top soil, seed mix to include temporary irrigation and miscellaneous related items of work.