Change Order/Amendment No. 3 with Hill & Wilkinson General Contractors for the Firehouse Gastro Park Restaurant in the amount of $92,827.20 for operator design changes, cooler panel credit, construction testing, restroom container skirt enclosure, kitchen container finishes, existing drainage improvements, stage container wood deck, bar layout changes, additional bar equipment, stage container finishes, purchase of final kitchen equipment, service counter air curtain and electrical code revisions
Presenter
Andy Henning, Senior Building and Construction Projects Manager
Recommended Action
Approve
Analysis
On October 11, 2016 the City Council awarded the Construction Manager at Risk (CMAR) contract to Hill & Wilkinson General Contractors (16-6086) for pre-construction services in the amount of $10,000. This award provided for CMAR services including development of project estimates, preliminary construction schedules, value engineering proposals and constructability review during the Design Phase of the Firehouse Gastro Park Restaurant project.
The current Change Order/Amendment No. 3 in the amount of $92,827.20 is divided as follows:
$13,755.07 for design changes required to coordinate with the planned operations of the facility
-$2,148.75 credit for damage to one panel of the exterior cooler during installation
$12,069.26 for construction material testing as implemented by the Construction Manager
$3,545.42 for design and installation of the lower skirt enclosure around the restroom container
$14,733.94 for reinstatement of the event lawn kitchen container for additional menu variety and increased capacity to serve patrons
$9,669.36 for continuous trench drain installation along the property line of the building to the east of the Firehouse Restaurant event lawn
$9,293.32 for wood decking provisions at the stage container along with container modifications to include storage space and a green room for visiting artists ...