Skip to main content
File #: 19-8897    Version: 1 Name: Fire Station 4+6 Change Order/Amendment No. 3 with Key Construction in the amount of $144,319.71
Type: Agenda Item Status: Consent Agenda
File created: 4/25/2019 In control: Engineering
On agenda: 5/7/2019 Final action: 5/7/2019
Title: Fire Station 4+6 Change Order/Amendment No. 3 with Key Construction in the amount of $144,319.71 for extended contractor General Conditions due to weather impacts, added interior door, catwalk structure, louver covers, sanitary sewer piping revisions, added power, low voltage controls, dimmer switches, exhaust fan relocation, electrical panel changes, removal of equipment bay drainage, ceiling fan supports, landscape revisions, tile changes, removal of additional trench drain, elimination of sand/oil separator, tree removal and final project buy-out/scope coordination
Attachments: 1. 617.04 FS 4 and 6.pdf
From
max

Title
Fire Station 4+6 Change Order/Amendment No. 3 with Key Construction in the amount of $144,319.71 for extended contractor General Conditions due to weather impacts, added interior door, catwalk structure, louver covers, sanitary sewer piping revisions, added power, low voltage controls, dimmer switches, exhaust fan relocation, electrical panel changes, removal of equipment bay drainage, ceiling fan supports, landscape revisions, tile changes, removal of additional trench drain, elimination of sand/oil separator, tree removal and final project buy-out/scope coordination

Presenter
Andy Henning, Senior Building and Construction Projects Manager

Recommended Action
Approve

Analysis
On June 5, 2018 the City Council awarded the Construction Manager at Risk (CMAR) contract to Key Construction for pre-construction services in the amount of $15,000. This award provided for CMAR services including development of project estimates, preliminary construction schedules, value engineering proposals and constructability review during the Design Phase.

The current Change Order/Amendment No. 3 in the amount of $144,319.71 is divided as follows:
$117,270.00 for extended General Conditions due to necessary adjustments in project phasing along with significant weather delays to the project above and beyond the ordinary expected weather days contractually planned for $31,076.71 for added interior door at workout room, catwalk structure above apparatus bay, louver covers at code-required safe room, rerouting of sanitary sewer piping, added power provisions, additional low voltage controllers, new dimmer switches, relocation of exhaust fan and electrical panel changes -$4,027.00 credit for removal of apparatus bay drainage, ceiling fan supports, landscape revisions, tile changes, removal of trench drain, elimination of sand/oil separator, tree removal and final project buy-out/scope coordination

Change Order/Amendment No. 1 in the amount of $4,400,000 was app...