Professional engineering services contract with Freese and Nichols, Inc. in the maximum amount of $219,000, for professional design and surveying services for Oakdale Road paving and drainage improvements between Roy Orr Blvd and State Highway 161
Presenter
Romin Khavari, City Engineer
Recommended Action
Approve
Analysis
This contract provides for the roadway design of 3,600 feet of 4-lane divided thoroughfare in Oakdale Road between Roy Orr Blvd to the west and SH 161 to the east; this contract also provides for traffic signal design at the intersection of Oakdale Road and Roy Orr Blvd. This contract provides for the following services:
-Segment 1: full design and construction phase from Roy Orr Blvd and 600 feet to the east through city owned right of way which is an adjusted alignment for Roy Orr Blvd. Some additional Right-of-way will be needed for this section to transition into the existing pavement.
-Segment 2: 30% design of the remaining 3,000 feet eastward to SH 161 in anticipation of possible future development. Final design of this segment will be performed under a separate contract in 2019 and beyond.
Design services under this contract are scheduled to begin in late August 2014 with completion by the end of April 2015. Construction services for Segment 1 will follow.
Financial Consideration
Funding in the amount of $219,000 is available in Street Capital Projects Fund (400192) WO#01406303 (Oakdale - Roy Orr to 161)