Title: Construction Manager at Risk (CMAR) Contract with Modern Contractors for pre-construction services for phase two additions and renovations to the Fleet Services Service Center in the amount of $1,000 and approve a Construction Services Fee of 2.50% to be applied to the actual approved construction costs for phase two of the Fleet Services Service Center additions and renovations
Attachments: 1. 18-8084 Srv Ctr Ph II 618.169.pdf
From
max

Title
Construction Manager at Risk (CMAR) Contract with Modern Contractors for pre-construction services for phase two additions and renovations to the Fleet Services Service Center in the amount of $1,000 and approve a Construction Services Fee of 2.50% to be applied to the actual approved construction costs for phase two of the Fleet Services Service Center additions and renovations

Presenter
Andy Henning, Senior Building and Construction Projects Manager

Recommended Action
Approve

Analysis
On April 3, 2018 the City Council approved an architectural design contract with Magee Architects (18-7761) for design of phase two renovations and additions to the Fleet Services Service Center in the amount of $453,425, a 5% design contingency in the amount of $22,671, and a not-to-exceed $14,575 reimbursable allowance for a total of $490,671. The goal was to complete all necessary design associated with the recommendations and improvements of the comprehensive facility review to meet the ever-changing needs of the growing city.

With the design process nearing a point of needing important cost estimation and constructability review, an RFP #18108 solicitation was advertised by the City in accordance with State law with respondents to the RFP required to submit their proposals no later than July 19, 2018. Seven (7) Construction Managers responded to the RFP. The selection committee reviewed and scored all of the proposals and ultimately made the decision that the selection of Modern Contractors was in the greatest interest and represented the best overall value to the City of Grand Prairie. In addition, a decision to not conduct optional interviews was made based on existing knowledge of the responding Construction Managers and the respective/corresponding dispersion of pricing. As a result, Modern Contractors is being recommended to City Council for the Pre-Construction CMAR contract award.

While the committee appreciated having outstanding groups...