From
max
Title
Interlocal Agreement with the City of Grand Prairie and the Trinity River Authority of Texas for the construction of Mountain Creek Fish Creek Interceptor, Segment MC-3 Project in conjunction with the City's Great Southwest Parkway Improvements
Presenter
Ron McCuller, Director of Public Works and Romin Khavari, City Engineer
Recommended Action
Approve
Analysis
The Mountain Creek Interceptor System is one of the five major interceptor systems that convey wastewater to the TRA Central Regional Wastewater Treatment Plant. TRA plans to re-construct a portion of the Mountain Creek Fish Creek Interceptor, Segment MC-3 Project in North Fork of Fish Creek (Prairie Creek) of the City of Grand Prairie.
Approximately 288 linear feet of 36-inch diameter of this above Wastewater interceptor pipeline is proposed to cross the Right-Of-Way of Great Southwest Parkway at the proposed future Great Southwest bridge at Prairie Creek. The City of Grand Prairie has plans to construct the roadway, bridge and utility improvements for phase I of Great Southwest Parkway from Sara Jane to Forum Drive. In order to avoid having two contractors working in the same area, City and TRA Staff have discussed including this portion of the TRA main as part of the City Project. In order to perform this work, TRA has proposed the attached interlocal agreement to allow the City to construct this segment in conjunction with the roadway and bridge improvements. The City will be reimbursed for the TRA interceptor construction costs.
The agreement provides that TRA will pay for the line segment not to exceed $275,000. Should the City's bid exceed this amount for this section of pipeline, TRA will reconsider this cost prior to the city awarding the construction contract.
Financial Consideration
No funding required for this interlocal agreement.