Skip to main content
File #: 19-8648    Version: 1 Name: Warmack Library Change Order/Amendment No. 4 with Pogue Construction in the amount of $58,945.22 for equipment lift rental, window tinting, millwork revisions, hardware changes, added painting, expansion of cement board, extension of wall construction, br
Type: Agenda Item Status: Consent Agenda
File created: 1/25/2019 In control: Engineering
On agenda: 2/5/2019 Final action: 2/5/2019
Title: Warmack Library Change Order/Amendment No. 4 with Pogue Construction in the amount of $58,945.22 for equipment lift rental, window tinting, millwork revisions, hardware changes, added painting, expansion of cement board, extension of wall construction, brick infill, art panel adjustments, electrical connections, wall framing revisions, carpet type change, protective corner guards, emergency lighting and new louver credit
Attachments: 1. 617.17 Warmack.pdf
From
max

Title
Warmack Library Change Order/Amendment No. 4 with Pogue Construction in the amount of $58,945.22 for equipment lift rental, window tinting, millwork revisions, hardware changes, added painting, expansion of cement board, extension of wall construction, brick infill, art panel adjustments, electrical connections, wall framing revisions, carpet type change, protective corner guards, emergency lighting and new louver credit

Presenter
Andy Henning, Senior Building and Construction Projects Manager

Recommended Action
Approve

Analysis
On August 15, 2017 the City Council awarded the Construction Manager at Risk (CMAR) contract to Pogue Construction for pre-construction services in the amount of $7,500. This award provided for CMAR services including development of project estimates, preliminary construction schedules, value engineering proposals and constructability review during the Design Phase.

The current Change Order/Amendment No. 4 in the amount of $58,945.22 is divided as follows:
$7,069.29 for additional lift equipment rental cost due to site access restrictions
$8,070.78 for tinting of existing glazing window locations to match new glazing provisions
$6,000.00 for millwork and countertop revisions
$936.68 for relocation of existing sprinkler to coordinate with new ceiling design
$4,165.00 for hardware changes to the retractable interior glazing system at children and adult programming spaces
$9,190.08 for painting of the existing entry stucco and metal shade canopy
$1,113.41 for added cement board backing in restroom as required for tile extents
$4,088.41 for extension of wall construction to roof metal deck above at mechanical room
$2,722.27 for brick infill of existing openings being abandoned
$6,206.84 for decorative entry art panel adjustments
$2,030.00 for additional electrical connections associated with new air handling unit
$4,263.97 for metal stud framing revisions
$425.87 for carpet change at office entry door
$1,023.88 fo...

Click here for full text