Skip to main content
File #: 15-5163    Version: 1 Name: Land Acquisition - Fish Creek Linear Park
Type: Agenda Item Status: Consent Agenda
File created: 11/5/2015 In control: Parks & Recreation
On agenda: 11/17/2015 Final action: 11/17/2015
Title: Acquisition of property for extension of Fish Creek Linear Park
Attachments: 1. 15-5138 Fish Creek Parks

From

Linda Townley

 

Title

Acquisition of property for extension of Fish Creek Linear Park

 

Presenter

Rick Herold, Director of Parks, Arts and Recreation

 

Recommended Action

Approve

 

Analysis

Fish Creek Linear Park was planned to be a continuous trail linkage extending from the Arlington/Grand Prairie corporate boundary to the city limits of Dallas.  Three phases of development are complete and in place consisting of 110 acres and 2.3 linear miles of multipurpose trail.

 

In 2007, negotiations were begun for a tract of land adjacent to Matthew Road.  Concurrently, design plans were initiated for linear park development on this tract which would allow connection to the existing trail and planned parking lot to be developed as part of the Lake Ridge Parkway extension.

 

The tract was subsequently acquired by Texas Midstream, a subsidiary of Chesapeake Energy.  Land negotiations were stymied due to gas drilling issues at that time. 

 

Recently, staff found a willingness of Texas Midstream representatives to negotiate with the City to disperse of the tract.  The 8.02 acre tract was appraised at a value of $139,302.  Texas Midstream is also proposing to donate 2.346 acres.

 

The acquisition provides a direct connection and continuation of linear park development and staff recommends acquisition of the property.

 

The project was presented and approved by Finance and Government Committee on November 3, 2015.

 

Financial Consideration

Funding is available from the Street Capital Projects Fund (400192) WO #05503903 (Fish Creek Bike Pedestrian Path) 68610 (ROW/Easement/Land Purchase).